Renovation Progress!

Day 26 and the outside is beginning to look more finished.  All walls are in and the wall board has been taped, ready for texturing.  We are about to choose paint colors!

Stucco has been applied

Trim around windows added, porch will be built soon

Mr. Ripley loves "his" studio

North side, facing the trails

Porch/trellis wood will be attached soon

Tuesday, April 24, 2012

Renovation Progress!


Day 22 of the Garage Transformation !  Starting to look like rooms instead of a garage!

Skylight is framed out 


Wallboard gets added....

temporarily covering windows and doors!

Looking so different now!




Monday, April 16, 2012

Renovation Progress


Day 15.  Most of the work is being done inside right now, fine tuning things like plumbing, ducting, and electrical outlet placement.  Although the changes are smaller and more subtle, it still spells progress!




Thursday, April 12, 2012

Renovation Progress

It's not windy in here anymore!

Day 14....exterior walls ready for stucco; all doors and windows are in;  HVAC duct work is coming along nicely; tomorrow we meet with the electrician to determine locations for lights, outlets, switches etc.  ("Waiting for the Electrician or someone like him")  














Bathroom is starting to take shape.





















Duct work in the ceiling























It will be warm in the winter and cool in the summer

West side of the garage....soon to be our office/storage area

Bill's space and my studio....looking good! 

Tuesday, April 10, 2012

Renovation Progress

Day 12 and windows are in, plumbing is moving along, HVAC begins!

Plumbing is taking shape

Ripley is wondering what's going on

The view from Bill's shop space, with 3 windows and a doorway
The front of the garages.... windows are in!



The long view...it's looking better every day!

Friday, April 06, 2012

Renovation Progress

 Day 10, and all is well!


The framing is done, to define the 3 separate spaces.  This is Kat's studio, looking through the bathroom/mudroom to Bill's workshop

This is going to be where Bill will be spending his time, building and restoring guitars!


Kat enjoys her studio along with Ripley and a little glass of something good on a Friday night!
 No more garage doors!

Kat's studio

The long view of the garage renovation.

Thursday, April 05, 2012

Renovation Progress

Day 9, evening:  This is going to be the room in between Bill's shop and my studio.  It will include a handicapped bathroom and a utility room with a sink, counter top, storage and a skylight!  There will be doors to the utility room from both of our spaces.

Framing begins!

Ripley loves to check out the progress every day!

This room sits between our two work spaces

Still looks like a big garage....but not for long!

Renovation Progress

 Day 8, and the skylights are in, concrete has been poured to cover up the plumbing, and it looks better every day!

Tuesday, April 03, 2012

Renovation Progress

 Day 7.....windows cut out; plumbing inspection completed; ready for skylights!  AND....our wonderful crew might possibly be ahead of schedule!

Monday, April 02, 2012

Renovation Progress

Day 6! Windows are cut out and framed, plumbing is in place for inspection tomorrow, and I chose toilets, faucets, etc.  We are very impressed with our architect and contractor, Prescott Renovations.  Tom Reilly and Mike Bevier are a pleasure to work with.  So far, so good!

As the renovation progresses, our neighbor's dog, Clancey, supervises

Plumbing ready for inspection tomorrrow

Windows get framed, Day 6!

View from Kat's studio window!